Sample question 1 — Understanding Agile Release Trains
A newly formed Agile Release Train is preparing for its first PI Planning event. The RTE notices that teams have not yet established their team-level backlogs or identified their first features. What should the RTE do to improve readiness before the event?
- A. Help teams create initial backlogs and a draft feature set
- B. Delay the planning event until all backlogs are fully refined
- C. Ask each team to plan independently and merge plans later
- D. Proceed with the event and let teams define work during planning
Answer: A. Option A is correct because the RTE should help teams establish initial backlogs and a draft feature set so that PI Planning can be productive and focused on coordination. Option B is incorrect because delaying the event indefinitely undermines the cadence and does not build the needed readiness. Option C is incorrect because independent planning without a shared draft feature set defeats the purpose of the train-level event. Option D is incorrect because proceeding without any backlog or feature context leads to uncoordinated planning and poor outcomes.