Sample question 1 — Benefits Realization
A logistics company has approved a fleet-tracking initiative expected to reduce fuel costs by 12 percent within two years. Six months into the project, the sponsor asks the benefits manager to show whether the target is still achievable. The benefits manager finds that no baseline fuel consumption data was captured before the project began. Which action should the benefits manager take first to enable credible benefits realization?
- A. Reconstruct a baseline from historical fuel records and document the assumptions used
- B. Wait until the project closes and compare actual fuel costs with the original 12 percent target
- C. Ask the finance department to adjust the 12 percent target to match current fuel consumption
- D. Report that benefits realization cannot be measured because the baseline was never captured
Answer: A. Option A is correct because benefits realization depends on a credible baseline, and reconstructing one from historical records with documented assumptions restores the ability to measure progress. Option B is incorrect because waiting until project closure removes the opportunity to intervene while the initiative can still be corrected. Option C is incorrect because adjusting the target to current consumption masks performance rather than measuring it against the original intent. Option D is incorrect because abandoning measurement is not an acceptable governance outcome when historical data can support a reconstructed baseline.